Project Overview

Marcus was brought in early to help execute MRGA’s strategic plan, we helped put together an agronomy site design that was implemented in phases over a 6-year period. The first facility, was a 36,000 ton dry fertilizer building with unit train capabilities as well as retail blending and wholesale operations with rail pit designed for receiving at 800 tph. The next project was a 48,936 sq. ft. facility that housed liquid chemical and package storage, seed storage warehouse and treatment area, with a large maintenance shop. Next was a 3.9 million bushel flat grain storage facility. And most recently was a 3,600 sq. ft. addition to their chemical warehouse.

Facility Size
48,936 sq. ft. chemical warehouse
36,000 tons dry fertilizer
3.9 million bushel flat grain
Construction Type
Greenfield Site
Delivery Method
Design-Build