Project Overview

Simplot's existing dry fertilizer building had severe bulging of their existing bin walls, a sagging roof system, expansion issues with their cable system, and poor maintenance access to their upper conveyor. Marcus demolished, removed, replaced, stabilized and made additions to many sections of the building and roof. The overall corrections eliminate bulging and overall bin wall movements and allow Simplot workers to safely access their conveyor system.

Facility Size
30,000 tons dry fertilizer
Construction Type
Renovation and New Construction
Delivery Method
Design-Build